STATUS REPORT, MAY 2003
North Indian River Inlet Marina
Complex
Delaware Seashore State Park
State Managed Rehabilitation and Modernization
Plan
Status Report
May 2003
Prepared by: W. Britt Murray
Chief, Office of Design & Development
Division of Parks and Recreation
May 8, 2003
Safety Improvements:
Numerous safety improvement issues have been addressed since the Bond
Bill Committee notified the Division that we would indeed be responsible for
planning, design, reconstruction and operation of this marina as opposed to
a private partnership.
The deteriorated bulkhead, which caused sidewalk undermining and the
creation of sinkholes, has been rehabilitated. The old sidewalk was removed;
lower waterside structural members replaced/repaired, holes in bulkhead
patched, landside of bulkhead filled and grass planted. A new sidewalk has
been constructed immediately adjacent to the existing parking, approximately
30 feet from the bulkhead, thereby directing pedestrian traffic to use this
travel way as opposed to walking adjacent to the bulkhead. This repair to
the bulkhead was designed to protect landside structures and utilities and
to last at least until the entire structure is replaced in the winter of
2003.
New overhead light fixtures have been installed to replace the old,
sometimes inactive fixtures. This provides patrons with reliable lighting
for safety and security reasons.
Repairs to the docks have been completed in the form of the installation
of 'diamond-plate' aluminum plates in walkways and gussets (triangular
structural components joining main walkways with finger piers). This plating
addresses severe deterioration of the old dock system. Before these repairs
were started, there were reports of people stepping on deteriorated sections
and having them break away and fall into the marina basin. Repairs have been
completed at over 190 locations throughout the dock system and are
anticipated to last until the entire dock system is replaced by the 2005
boating season. Also, during the gusset/walkway repairs, any power posts
determined to be electrically or structurally unsafe are being replaced. 50
Power posts have been replaced during this safety improvement work, the
majority of which are suitable for salvage and re-use on the replacement
docks as they will only be one or two years old.
Public Involvement:
To date, the Division has solicited input (via in person discussion and a
customer survey) and provided information to the general public and
slipholders on several occasions. A public open house was held on August
23rd to describe the conceptual plan for the reconstruction of the marina
and the associated schedule of activities (exactly as was voted on and
passed in May/June 2002 by the Committee).
The Division initially received a less than favorable reception from the
slipholders; specifically they stated that their interests were not being
addressed in as timely a fashion as they would have liked. Constructive
suggestions were offered regarding the scheduling of the Dry Stack storage
facility being constructed first and the associated loss of 25' wet slips,
even though, from the owners perspective, this was the most economically
feasible way to optimize the cash flow of generating early revenue to fund
improvements.
These comments were used to modify the plan approved by the Committee,
which had 192 wet slips ranging in size from 35' to 50' in length and 192
Dry Stack slips for 30' and under boats. The slipholders message was clear,
"build new docks, dredge the marina basin and rectify electric problems on
the docks as quickly as possible". We utilized their comments to modify the
conceptual plan and the associated schedule of activities. These modified
plans were presented to the group at the second meeting on November 1st.
In essence, the new schedule reflects the following; construction of
one-half the docks, with upgraded electric, one-half the dredging, the
construction of the new bulkhead, boat ramp and travel lift completed by the
2004 boating season as opposed to the old plan which would not have these
components replaced until the 2006 boating season. The current plan now has
274 wet slips and 174 Dry Stack slips. This change in the number of wet
slips has increased the cost of the reconstruction by approximately $2
million. This additional capital expenditure can be absorbed by utilizing
federal US Fish & Wildlife funds for the boat ramp construction and
modifying the timing and value of principle and interest payments to the
Parks Endowment fund, while still remaining within the $8.8 million and
twenty year payback limits established by epilogue language.
The slipholders were most appreciative of this modified plan and schedule
at our meeting on November 1st and showed strong support for the Division to
accomplish this. By making these modifications to the plan, we can assure
every current slipholder will have a wet slip, if they choose to stay in a
wet slip, when the reconstruction is complete.
The Division held a progress meeting on April 4, 2003 to update
slipholders and the general public on the status of design and present the
most recent plans and schedules for construction. The presentation was very
well received and public continued their support for the project.
In conjunction with public workshops sponsored by DelDOT for the Indian
River Inlet Bridge replacement, Parks was invited to also display current
plans for the northside improvements. As you can imagine changes to the
existing bridge have a significant impact on all aspects of operation of
Delaware Seashore State Park, especially immediately north and south of the
inlet, and the two agencies are working closely to insure that the finished
product not only provides for a location sensitive design for the bridge,
but must enhance the neighboring park regarding access, aesthetics and
public use. Parks attended these workshops and presented plans to the
general public on February 26th, April 23rd and April 24th. The most common
comment heard from attendees/participants was “We are so pleased the
State is keeping this marina and northside park instead of giving it away
forever to the private group.”
The Division has created a website (www.irimarina.com)
to keep interested parties apprised of the planning and design status and to
continue to solicit comments from our users. The website went ‘on-line’ in
January 2003. As of April 26th, we have had 24,511 visitors, many who
submitted questions or comments via a ‘feedback’ component on the site.
Marina Planning, Design, Construction:
The Division has hired the following professional services to assist in
the planning, design and construction management for the reconstruction;
Baker Associates, Landscape Architects/Planners to act as Owner's
professional expert regarding land use, circulation (both vehicular and
pedestrian), site layout and design, aesthetics, customer orientation,
landscaping, etc. We have also retained the services of Applied Technology
Management (ATM), internationally recognized experts in the field of
environmental and coastal engineering to address all water-based regulatory
permitting, design and construction documentation for the reconstruction of
the marina basin including; Wet Slips, Dry Stack storage, fuel dock
upgrades, boat ramp reconstruction, bulkhead replacement and associated
necessary infrastructure.
The schedule to accomplish these tasks has been very aggressive in order
to meet our patron's wishes. State Marina Permit applications were submitted
April 22nd so that we will be able to bid, award and begin construction by
October 2003. The window for dredging is limited to September through
December and we must be able to accommodate our customers by April 2004.
Corps of Engineers permit application was submitted May 7, 2003. Coastal
Zone Consistency Statement was submitted May 7, 2003.
In addition to the assistance from our consultants, an in-house committee
comprised of a staff engineer, architect, revenue manager, marina manager,
construction project managers and Parks section managers meet weekly to
review the progress of construction planning, develop policies for and
evaluate the proposed operational issues.
Staff have also toured privately run facilities to ascertain the most
effective and efficient management principles, maintenance and operation
procedures and customer service practices utilized by these businesses.
Preliminary plans were submitted to and reviewed by the Joint Permit
Processing Committee on December 19, 2002. This a group of regulatory
officials representing; the Corps of Engineers, the US Fish and Wildlife
Service, the state Fish and Wildlife Division, the State Historic
Preservation Office, the State Water Resources Division specifically
Wetlands and Subaqueous land permitting personnel. Based on that review,
plans have been modified and permit applications have been submitted as
noted above.
Overnight Accommodations Planning, Design, Construction:
The Division is conducting all planning, design and construction
management for the various overnight accommodations and architectural
building modifications in-house.
The twelve cottages will be constructed along the inlet in time for the
2004 season. Advertisement for bids for this cottage complex began on May
7th, construction is scheduled to be complete by April, 2004.
The improvements to the campground should be completed by the 2005
season. Scheduling of this activity is dependent on the final alignment and
design for the replacement bridge over the Indian River Inlet. DNREC and
DelDOT are working cooperatively to ensure neither party is negatively
impacted, but rather synergistically enhanced.
We have had very successful experiences with the various overnight
accommodations opportunities we offer at other parks; camping (both tent and
RV), cabins and yurts at Lums Pond, Killens Pond, Trap Pond, Cape Henlopen
and other areas within Delaware Seashore State Park.
Please recall that although these improvements are funded via federal
Land and Water Conservation Funds, all net revenue generated (for a period
of eight years) at these facilities will be utilized to fund marina
improvements and/or pay back the loan from the Endowment Fund.
List of Plans:
• Project
Description
• Overall Site
Development Plan
• 2004 Boating
Season
• 2005 Boating
Season
• 2006 Boating
Season
• 2007 Boating
Season
• Cottages Site Plan
• Cottages Marketing Display
PHOTOS
Gusset and Dock Repairs
• Before repairs – 2 photos
• After repairs – 2 photos
Pier 'C', deteriorated "gusset"

Close-up of deteriorated "gusset"

Pier 'A': Example of completed ‘gusset’ repair

Pier 'A': Example of completed ‘gusset’ and dock repair

PHOTOS
Bulkhead and Sidewalk Repairs
• Before repairs – 3 photos
• After repairs – 3 photos
• Aerial photos – Nov. 1996 & Feb. 2003
Illustration of sidewalk settlement: Note how land side is dropped

Illustration of undermining sidewalk caused by fill material leaching
through holes in bulkhead and repairs in progress

Close-up of ‘sinkhole’ created by leaching of fill through holes in
bulkhead

New Sidewalk under construction: Note separation from bulkhead preventing
users from encountering ‘sinkholes’

Completed Sidewalk: North of Operations Building

Completed Sidewalk: South of Operations Building

Indian River Inlet Marina November 1996 Aerial View

MEDIUM (246 KB) •
LARGE (393 KB)
Indian River Inlet Marina February 2003 Aerial View

MEDIUM (218 KB) •
LARGE (2.0 MB)
Note: Sidewalk relocated from bulkhead to edge of parking. |