STATUS REPORT, DECEMBER 2002
North Indian River Inlet Marina
Complex
Delaware Seashore State Park
State Managed Rehabilitation and Modernization
Plan
Status Report
December 2002
Prepared by: W. Britt Murray
Chief, Office of Design & Development
Division of Parks and Recreation
December 16, 2002
Safety Improvements:
Numerous safety improvement issues have been addressed since the Bond
Bill Committee notified the Division that we would indeed be responsible for
planning, design, reconstruction and operation of this marina as opposed to
a private partnership.
The deteriorated bulkhead, which caused sidewalk undermining and the
creation of sinkholes, has been rehabilitated. The old sidewalk was removed;
lower waterside structural members replaced/repaired, holes in bulkhead
patched, landside of bulkhead filled and grass planted. A new sidewalk has
been constructed immediately adjacent to the existing parking, approximately
30 feet from the bulkhead, thereby directing pedestrian traffic to use this
travel way as opposed to walking adjacent to the bulkhead. This repair to
the bulkhead was designed to protect landside structures and utilities and
to last at least until the entire structure is replaced in the winter of
2003.
New overhead light fixtures have been installed to replace the old,
sometimes inactive fixtures. This provides patrons with reliable lighting
for safety and security reasons.
Repairs to the docks are underway in the form of the installation of
'diamond-plate' aluminum plates in walkways and gussets (triangular
structural components joining main walkways with finger piers). This plating
addresses severe deterioration of the old dock system. Before these repairs
were started, there were reports of people stepping on deteriorated sections
and having them break away and fall into the marina basin. These repairs
will be completed by the 2003 boating season and are anticipated to last
until the entire dock system is replaced by the 2005 boating season. Also,
during the gusset/walkway repairs, any power posts determined to be
electrically or structurally unsafe are being replaced.
Public Involvement:
To date, the Division has solicited input (via in person discussion and a
customer survey) and provided information to the general public and
slipholders on two occasions. A public open house was held on August 23rd
to describe the conceptual plan for the reconstruction of the marina and the
associated schedule of activities (exactly as was voted on and passed in
May/June by the Committee).
The Division initially received a less than favorable reception from the
slipholders; specifically they stated that their interests were not being
addressed in as timely a fashion as they would have liked. Constructive
suggestions were offered regarding the scheduling of the Dry Stack storage
facility being constructed first and the associated loss of 25' wet slips,
even though, from the owners perspective, this was the most economically
feasible way to optimize the cash flow of generating early revenue to fund
improvements.
These comments were used to modify the plan approved by the Committee,
which had 192 wet slips ranging in size from 35' to 50' in length and 192
Dry Stack slips for 30' and under boats. The slipholders message was clear,
"build new docks, dredge the marina basin and rectify electric problems on
the docks as quickly as possible". We utilized their comments to modify the
conceptual plan and the associated schedule of activities. These modified
plans were presented to the group at the second meeting on November 1st.
In essence, the new schedule reflects the following; construction of
one-half the docks, with upgraded electric, one-half the dredging, the
construction of the new bulkhead, boat ramp, travel lift and fuel dock
completed by the 2004 boating season as opposed to the old plan which would
not have these components replaced until the 2006 boating season. The
current plan now has 274 wet slips and 174 Dry Stack slips. These numbers
could change slightly as we progress further with design. This change in the
number of wet slips has increased the cost of the reconstruction by
approximately $2 million. This additional capital expenditure can be
absorbed by utilizing federal US Fish & Wildlife funds for the boat ramp
construction and modifying the timing and value of principle and interest
payments to the Parks Endowment fund, while still remaining within the $8.8
million and twenty year payback limits established by epilogue language.
The slipholders were most appreciative of this modified plan and schedule
at our meeting on November 1st and showed strong support for the
Division to accomplish this. By making these modifications to the plan, we
can assure every current slipholder will have a wet slip, if they choose to
stay in a wet slip, when the reconstruction is complete.
The Division is finalizing the creation of a website to keep interested
parties apprised of the planning and design status and to continue to
solicit comments from our users. We hope to have the website up and running
by the end of January 2003.
Marina Planning, Design, Construction:
The Division has hired the following professional services to assist in
the planning, design and construction management for the reconstruction;
Baker Associates, Landscape Architects/Planners to act as Owner's
professional expert regarding land use, circulation (both vehicular and
pedestrian), site layout and design, aesthetics, customer orientation,
landscaping, etc. We have also retained the services of Applied Technology
Management (ATM), internationally recognized experts in the field of
environmental and coastal engineering to address all water-based regulatory
permitting, design and construction documentation for the reconstruction of
the marina basin including; wet slips, Dry Stack storage, fuel dock
upgrades, boat ramp reconstruction, bulkhead replacement and associated
necessary infrastructure.
The schedule to accomplish these tasks is very aggressive in order to
meet our patron's wishes. We must have the design completed to the point
where permit applications can be submitted by April 2003 in order to be able
to bid, award and begin construction by October 2003. The window for
dredging is limited to September through December and we must be able to
accommodate our customers by April 2004.
In addition to the assistance from our consultants, an in-house committee
comprised of a staff engineer, architect, revenue manager, marina manager,
construction project managers and Parks section managers meet weekly to
review the progress of construction planning, develop policies for and
evaluate the proposed operational issues.
Staff have also toured privately run facilities to ascertain the most
effective and efficient management principles, maintenance and operation
procedures and customer service practices utilized by these businesses.
Preliminary plans will be submitted to and reviewed by the Joint Permit
Processing Committee on December 19th. This a group of regulatory
officials representing; the Corps of Engineers, the US Fish and Wildlife
Service, the state Fish and Wildlife Division, the State Historic
Preservation Office, the State Water Resources Division specifically
Wetlands and Subaqueous land permitting personnel.
Overnight Accommodations Planning, Design, Construction:
The Division is conducting all planning, design and construction
management for the various overnight accommodations and architectural
building modifications in-house.
The twelve cottages will be constructed along the inlet in time for the
2004 season.
The improvements to the campground should be completed by the 2005
season.
We have had very successful experiences with the various overnight
accommodations opportunities we offer at other parks; camping (both tent and
RV), cabins and yurts at Lums Pond, Killens Pond, Trap Pond, Cape Henlopen
and other areas within Delaware Seashore State Park.
Please recall that although these improvements are funded via federal
Land and Water Conservation Funds, all net revenue generated (for a period
of eight years) at these facilities will be utilized to fund marina
improvements and/or pay back the loan from the Endowment Fund.
Letter to Slip holders, October 18, 2002

Comparison of August 23rd and November 1st Plans

PHOTOS
Gusset and Dock Repairs
• Before repairs – 2 photos
• After repairs – 2 photos
Pier 'C', deteriorated "gusset"

Close-up of deteriorated "gusset"

Pier 'A': Example of completed ‘gusset’ repair

Pier 'A': Example of completed ‘gusset’ and dock repair

PHOTOS
Bulkhead and Sidewalk Repairs
• Before repairs – 3 photos
• After repairs – 3 photos
Illustration of sidewalk settlement: Note how land side is dropped

Illustration of undermining sidewalk caused by fill material leaching
through holes in bulkhead and repairs in progress

Close-up of ‘sinkhole’ created by leaching of fill through holes in
bulkhead

New Sidewalk under construction: Note separation from bulkhead preventing
users from encountering ‘sinkholes’

Completed Sidewalk: North of Operations Building

Completed Sidewalk: South of Operations Building
 |